Project information

This reference documents the preparation and international shipment of a MEGA MPR 3.1 production line to Isebania, Kenya. The equipment and project components were checked at MEGA before dispatch and prepared for secure transport.

Project scope

The shipment was prepared as a coordinated production package, with the main machine and supporting components organised for delivery.

  • MPR 3.1 semi-automatic concrete block, paving stone and curbstone production equipment
  • Material preparation and transfer equipment
  • Electrical and hydraulic control units
  • Production trolleys and project accessories
  • Concrete block mould
  • Paving stone mould
  • 110 kVA generator

Shipment preparation

The equipment was inspected, grouped and secured according to the transport plan. The images below show the machinery and project components during the preparation and loading stages; they do not represent a completed on-site installation.